The Internet Company Projects

Company: The Internet Company
Manager: Rick
Start Date: August 14, 2004
Finish Date: September 24, 2004
Duration: 41d 17h
Report Date: August 14, 2004

Gantt Chart


*** Note: Gantt chart requires CSS capability. ***
WBS Name Work Week 33, 2004 Week 34, 2004 Week 35, 2004 Week 36, 2004 Week 37, 2004
14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
1 Create Webmail software 7d
Rick
2 Mail in Contract 1h
Rick
3 Negotiate Field Connection 5d
Rick
4 Firm up collocation 2d
Rick
5 Find DSLAM software. 1d
Rick

Tasks

WBS Name Start Finish Work Priority Cost
1 Create Webmail software Aug 14 Sep 2 7d 2 1,400
2 Mail in Contract Aug 16 Aug 18 1h 1 5.6
3 Negotiate Field Connection Aug 18 Sep 7 5d 1 720
4 Firm up collocation Aug 18 Sep 7 2d 1 112
5 Find DSLAM software. Aug 16 Sep 24 1d 2 12

Resources

Name Short name Type Group Email Cost
My Time Rick Work aredridel@theinternetco.net 50